Timeline

Planning Process Timeline

Visioning: August 2016 - February 2017

Purpose

Using multiple sources of information, data and feedback, the School Board will identify a vision for high schools that prepare young people to graduate ready to enter adult life.

We will take into account that (1) our current goal is life-readiness-oriented, and (2) we already have a wealth of background on this work by staff and community

​Key Activities/Terms

  • Consultant/Facilitator
  • School Board Work Sessions
  • Advisory Committee
  • Virginia Department of Education (VDOE) Changes
  • Site Visits/VDOE Grant Recipients
  • Research Database
  • Stakeholder Activities

​Outcome

Staff report to School Board on a recommendation

Facility Planning Study: ​February 2017 - October 2017

Purpose

Solicitation and study: Identify options and alternatives to address capacity issues at Albemarle High School as well as the facility impact on current facilities based on the vision articulated in previous stage.

​Key Activities/Terms

  • Consultant to produce and analyze options/alternatives
  • Community meetings to receive feedback
  • School Board Work Sessions

​Outcome

  • Recommendation for a solution to capacity issues at Albemarle
  • Recommendation for facility improvements to current facilities

Decision/Approval: November 2017 - April 2018

Purpose

Take action on recommendations of previous two stages.

​Key Activities/Terms

  • School Board Meeting(s)
  • Community Meetings / Hearings
  • Board of Supervisors Meeting(s)

​Outcome

  • School Board CIP Request for facility renovations, additions, and/or new school
  • Board of Supervisors approval of requested project